Tulsa International Airport

Repaving Runway 36R

The Tulsa Metropolitan area encompasses an estimated 1 million people who trust Tulsa International Airport for their travel needs. The busy airport relies heavily on its three runways and couldn't afford to shut down its only two air carrier runways for the time it would take to make needed repairs. Garver's Construction Observation Team subcontracted to Atkins North America. Together, they worked with the airport to shut pieces of the runway down for short periods of time rather than shutting the whole runway down for a long period of time.

"Tulsa runs a busy airport," said Garver Senior Construction Observer Petey Chambless. "Adhering to the phased design and staying ahead of the construction's progress was absolutely essential to maintaining our schedule, which minimizes closures and allows Tulsa International Airport to continue to run its business the way it needs to."

The airport began repaving sections of Runway 36R in 2011 and finished the final phase of the project—the intersection of two runways—this year. To minimize impact to airport operations, construction was limited to weekends. For the final phase, crews worked through the night for 12 weekends from 11 p.m. Friday to 2:30 p.m. Monday, tearing out the old pavement and putting in the new pavement in time for traffic to utilize the intersection by the beginning of the week.

"Garver's Construction Observation Team makes sure the contractors do everything according to the design," said Construction Observer Billy Yates. "Watching the amount of communication and coordination between all the different contractors and subcontractors out here—for this project, with this tight of a deadline—it was an impressive thing to see."

 
For more information, view our
services portfolio at GarverUSA.com
Click here to subscribe

 

Also in this issue

Director's Insight
Director of Construction Services Explains the Value of Attentiveness and Proactivity
Water Reclamation Center
Energy Optimization Upgrade of Water Reclamation System
Don Tyson Parkway Interchange
New Interchange Supports Growth
North Little Rock Municipal Airport
Lighting Rehabilitation

 

Recommended articles

BNA Geothermal Cooling System
Innovative Solution
Strother Field
Runway 17-35 Rehabilitation
Cynthiana-Harrison County Airport
Airfield Improvements
View our services and projects portfolio.

Inside Garver - Garver's Blog.

Careers - Career opportinities with Garver.

Follow Us



Who We Are  |   Markets  |   Awards  |   Blog  |   Planroom  |   IQ Magazine  |   Locations and Contacts  |   Join Us
Transportation  |   Aviation  |   Water  |   Federal  |   Facilities Design  |   Power  |   Development  |   Construction Services  |   Survey  |   AssetMax
Terms of Use  |   Site Map  |   Info Exchange

By using this web site, you accept the terms of use. ©2013 Garver