Dallas Love Field continues to play a growing role in the nation’s aviation network, supporting both commercial service and a steady flow of general aviation traffic. As demand has increased over time, so has the need to modernize and strengthen the airfield to keep pace.

In January 2024, Love Field began its $64 million Taxiway Alpha rehabilitation and Runway 13L-31R runway safety area improvements focused on replacing 50-year-old pavement, eliminating FAA-defined hot spots and lowering sections of Taxiway Alpha over three feet to meet modern aircraft pavement grade standards.  

Everything changed when Dallas was announced as a major host and international broadcasting hub for soccer’s biggest stage and this summer’s tournament. Love Field’s GA side, anchored by Taxiway Alpha, was expected to see a sharp increase in private aircraft tied to media, teams, and international activity. No penalty whistle here. Just an adjustment in tempo and acceleration in the schedule to meet the excitement.

The project was structured to maintain continuous airfield access during construction through seven individual phases of work. One key milestone was a planned, 85-day Runway 13L-31R closure to construct three new taxiway connectors providing connections from the runway to Taxiway Alpha.  

Planning efforts for this closure required coordination between the Department of Aviation, Garver as design engineer, construction manager HNTB, contractor Flatiron, airlines, fixed base operators (FBOs), FAA Air Traffic Control, and the based tenants. An 85-day closure window was nailed down with airlines and the east side FBOs a year in advance to minimize impacts and deliver the work in 2024.  

With a defined window in place, the team executed against a clear plan, completing this work inside the runway environment ahead of schedule.  

Maintaining performance in a high-demand environment

Airfield projects demand coordination across operations, maintenance, construction, and the various stakeholders that use the airport. Regular communication and shared visibility into these schedules kept teams aligned as adjustments were made, further reinforced with a supplemental safety risk assessment (SRA) for the revised phasing plan.  

Garver’s initiation of the supplemental SRA provided early visibility into a potential hazard, allowing the team to proactively adjust phasing and avoid added workload for air traffic controllers. This decision was validated in the past year with the challenges the national airspace encountered due to staffing.  

Yet, this risk supercharged the collaboration between all stakeholders to identify every possible opportunity to deliver this project ahead of schedule. The result was buy-in from the tower and tenants to allow for new temporary aircraft taxi paths that accelerated the project without disrupting ongoing operations.  

Originally planned for completion in August 2026, Garver and its partners, in coordination with the City of Dallas Department of Aviation, advanced Taxiway Alpha delivery to March 2026. All while maintaining performance, safety, and operational continuity on an active airfield.  

Good partners design for flexibility from the start

Early delivery reflects a disciplined approach to project management. For our team, careful planning, intentional phasing, and active coordination created the conditions to adjust our schedule without compromising performance. Milestones were achieved as planned, and Taxiway Alpha reopened on March 27, 2026, ready to meet anticipated increased GA demand this summer.  

For airports and public stakeholders, that forward-looking approach supports informed decision-making and reliable outcomes. Projects grounded in clear sequencing and strong partner alignment are better positioned to adapt to changing demands while maintaining long-term airfield operations and economic opportunity. At Dallas Love Field, this mindset helped the team move faster without losing footing, delivering critical airfield capacity ahead of schedule.  

Garver is proud to be part of the team helping position Love Field for the future and ready to support Dallas this summer as it takes the global stage for international soccer.